Neighborhoods › Midtown-Times Square › Building 1035707
Facade/scaffold work: The purpose of this phase of the project is to complete…, est. $50K
663 Fifth Avenue, Manhattan 10017 · Approved
| Job | M01411247 · Alteration |
|---|---|
| Category | facade/scaffold |
| Estimated cost | $49,980 |
| Scale | 8 → 8 stories; 1,666 sq ft |
| Work types | Structural |
| Filed | Aug 9, 2026 |
| Professional | Rjc Engineers |
| Building | BIN 1035707 · BBL 1012880003 |
| Official record | DOB NOW job M01411247 |
DOB description
M01411247-I1: The purpose of this phase of the project is to complete the separation of the buildings located at 663 and 655 Fifth Avenue. Existing openings on masonry party walls are to be infilled with CMU block from the cellar all the way up to the roof.
Status timeline
- Aug 9, 2026 — New job filed (Approved)
- Aug 11, 2026 — Plans approved (Approved)
Watch this block