Neighborhoods › East Midtown-Turtle Bay › Building 1036882
Interior renovation: Installation of partitions, doors, suspended ceiling…, est. $450K
950 3 Avenue, Manhattan 07036 · Permit Entire
| Job | M01350845 (4 filings: I1, P1, S1, S2) · Alteration |
|---|---|
| Category | interior renovation |
| Estimated cost | $450,000 |
| Scale | 32 → 32 stories; 9,000 sq ft |
| Work types | General Construction |
| Filed | Feb 8, 2026 |
| Professional | Natasha L Suzansky Architect |
| Building | BIN 1036882 · BBL 1013110040 |
| Official record | DOB NOW job M01350845 |
DOB description
M01350845-I1: Installation of Partitions, Doors, Suspended Ceiling, Millwork, Wall & Floor Finishes, Pantry, ADA Restroom and Renovate Existing Men's & Women's Restrooms on 32nd Floor. No Change to Occupancy, Use or Egress is Proposed
M01350845-P1: Install Air Conditioning & Transfer Air Ducts & Grilles, Volume Dampers, Supply Air Diffusers, Return Air Grilles, Exhaust Fans & Ducts & Replace Insulation on Existing H.P. Duct on 32nd Floor, Replace Roof-Top A/C Unit, Curb & Associated Ducts on Roof
M01350845-S1: Install Air Conditioning & Transfer Air Ducts & Grilles, Volume Dampers, Supply Air Diffusers, Return Air Grilles, Exhaust Fans & Ducts & Replace Insulation on Existing H.P. Duct on 32nd Floor, Replace Roof-Top A/C Unit, Curb & Associated Ducts on Roof
M01350845-S2: Install Pantry Plumbing Fixtures, Appliances, Elec. Water Heater, Mother's Rm Sink, Drinking Fountain, ADA Restroom & Assoc Piping, Replace Men's & Women's Restroom Plumbing Fixtures & Piping Back to Risers, Install Sprinkler System & Remove TCSP on 32 Fl
Status timeline
- Feb 8, 2026 — New job filed (Permit Entire) M01350845-I1
- Feb 9, 2026 — New job filed (Permit Entire) M01350845-S1
- Feb 9, 2026 — New job filed (Permit Entire) M01350845-S2
- Feb 9, 2026 — Permit issued — work can start (Mechanical Systems) M01350845-S1
- Feb 11, 2026 — Permit issued — work can start (Permit Entire) M01350845-S2
- Mar 2, 2026 — Permit issued — work can start (General Construction) M01350845-I1
- Mar 3, 2026 — Permit issued — work can start (Permit Entire) M01350845-I1
- Mar 15, 2026 — New job filed (Approved) M01350845-P1
- Mar 16, 2026 — Plans approved (Approved) M01350845-P1
- Mar 16, 2026 — Permit issued — work can start (Permit Entire) M01350845-S1
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01350845-I1-GC | General Construction | Permit Issued | Mar 2, 2026 | Jan 1, 2027 |
| M01350845-S2-EW-SP | Sprinklers | Signed-off | Feb 10, 2026 | Dec 1, 2026 |
| M01350845-S2-PL | Plumbing | Signed-off | Feb 10, 2026 | Nov 23, 2026 |
| M01350845-S1-MS | Mechanical Systems | Permit Issued | Feb 9, 2026 | Jan 1, 2027 |