Neighborhoods › Belmont › Building 2016263
Interior renovation: Conversion of existing buildings to bronx green jobs…, est. $4.1M
585 East Fordham Road, Bronx 10001 · Permit Entire
| Job | X01304699 (23 filings: I1, A1, P2, P9, A2, A3, P3, S4, S3, S1, P1, S9, P4, S5, S7, P8, Z2, S8, P7, Z1, S6, Z3, Z8) · Alteration CO |
|---|---|
| Category | interior renovation |
| Estimated cost | $4,079,984 |
| Scale | 2 → 2 stories; 19,683 sq ft |
| Work types | General Construction |
| Filed | Dec 8, 2025 |
| Professional | Matiz Architecture and Design |
| Building | BIN 2016263 · BBL 2032730265 |
| Official record | DOB NOW job X01304699 |
DOB description
X01304699-I1: Conversion of existing buildings to Bronx Green Jobs Center and associated interior and exterior work as shown on plans filed herewith.
X01304699-A1: Conversion of existing buildings to Bronx Green Jobs Center and associated interior and exterior work as shown on plans filed herewith.
X01304699-P2: Conversion of existing buildings to Bronx Green Jobs Center and associated interior and exterior work as shown on plans filed herewith.
X01304699-P9: Conversion of existing buildings to Bronx Green Jobs Center and associated interior and exterior work as shown on plans filed herewith.
X01304699-A2: structural work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-A3: structural work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-P3: structural work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-S4: structural work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-S3: Plumbing, Standpipe & Sprinkler work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-S1: Mechanical work associated with the proposed renovation and change of occupancy, as shown on plans filed herewith.
X01304699-P1: Partial demolition associated with the renovation of the existing building, as shown on the plans filed herewith.
X01304699-S9: Partial demolition associated with the renovation of the existing building, as shown on the plans filed herewith.
X01304699-P4: foundation and structural work associated with the proposed earthwork and change of occupancy, as shown on plans filed herewith.
X01304699-S5: foundation and structural work associated with the proposed earthwork and change of occupancy, as shown on plans filed herewith.
X01304699-S7: Civil Scope incl. the construction of the utility connection to the existing infrastructure in the public right-of-way to the renovated building as shown on plans filed herewith.
X01304699-P8: installation of pipe scaffolding. no change in use, occupancy or egress under this application. all work to comply with chapter 33 of nycbc
X01304699-Z2: installation of pipe scaffolding. no change in use, occupancy or egress under this application. all work to comply with chapter 33 of nycbc
X01304699-S8: Sub-Slab Depressurization System Set as shown on plans filed herewith.
X01304699-P7: installation of heavy duty sidewalk shed. no change in use, occupancy or egress. all work to comply with chapter 33 of nycbc
X01304699-Z1: installation of heavy duty sidewalk shed. no change in use, occupancy or egress. all work to comply with chapter 33 of nycbc
X01304699-S6: support of excavation as shown on plans filed herewith.
X01304699-Z3: installation of plywood construction fence. no change in use, occupancy or egress under this application. all work to comply with chapter 33 of nycbc
X01304699-Z8: INSTALLATION OF TEMPORARY ROOF PROTECTION AND SITE-SPECIFIC ENGINEERED ENCLOSURE/DEBRIS NETTING SYSTEM. ALL WORK TO COMPLY WITH CHAPTER 33 OF NYCBC. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Status timeline
- Dec 8, 2025 — New job filed (Permit Entire) X01304699-I1
- Dec 11, 2025 — New job filed (Permit Entire) X01304699-S1
- Dec 11, 2025 — New job filed (Permit Issued) X01304699-S3
- Dec 11, 2025 — New job filed (Permit Entire) X01304699-S4
- Dec 11, 2025 — New job filed (Permit Entire) X01304699-S5
- Dec 11, 2025 — New job filed (Permit Entire) X01304699-S6
- Dec 11, 2025 — New job filed (Approved) X01304699-S7
- Dec 11, 2025 — New job filed (Permit Entire) X01304699-S8
- Jan 5, 2026 — Plans approved (Approved) X01304699-S7
- Feb 12, 2026 — New job filed (Permit Entire) X01304699-S9
- Apr 1, 2026 — Permit issued — work can start (Mechanical Systems) X01304699-S1
- Apr 2, 2026 — Permit issued — work can start (Permit Entire) X01304699-S1
- Apr 5, 2026 — Permit issued — work can start (Structural) X01304699-S4
- Apr 6, 2026 — Permit issued — work can start (General Construction) X01304699-I1
- Apr 6, 2026 — Permit issued — work can start (Plumbing) X01304699-S3
- Apr 7, 2026 — Permit issued — work can start (Permit Issued) X01304699-S3
- Apr 7, 2026 — Permit issued — work can start (Foundation) X01304699-S5
- Apr 7, 2026 — Permit issued — work can start (Support of Excavation) X01304699-S6
- Apr 7, 2026 — Permit issued — work can start (Structural) X01304699-S9
- Apr 8, 2026 — Permit issued — work can start (Permit Entire) X01304699-S6
- Apr 8, 2026 — New job filed (Permit Entire) X01304699-Z1
- Apr 8, 2026 — Permit issued — work can start (Sidewalk Shed) X01304699-Z1
- Apr 9, 2026 — New job filed (Permit Entire) X01304699-Z3
- Apr 9, 2026 — Permit issued — work can start (Construction Fence) X01304699-Z3
- Apr 10, 2026 — Permit issued — work can start (Permit Entire) X01304699-Z3
- Apr 11, 2026 — New job filed (Permit Entire) X01304699-Z2
- Apr 12, 2026 — Permit issued — work can start (General Construction) X01304699-S8
- Apr 12, 2026 — Permit issued — work can start (Supported Scaffold) X01304699-Z2
- Apr 13, 2026 — Permit issued — work can start (Permit Entire) X01304699-S8
- Apr 14, 2026 — New job filed (Approved) X01304699-P1
- Apr 16, 2026 — Plans approved (Approved) X01304699-P1
- Apr 16, 2026 — Permit issued — work can start (Permit Entire) X01304699-S9
- May 4, 2026 — New job filed (Approved) X01304699-P2
- May 7, 2026 — New job filed (Approved) X01304699-P3
- May 7, 2026 — New job filed (Approved) X01304699-P4
- May 14, 2026 — Plans approved (Approved) X01304699-P4
- May 14, 2026 — Plans approved (Approved) X01304699-P3
- May 14, 2026 — Permit issued — work can start (Permit Entire) X01304699-S5
- May 26, 2026 — Plans approved (Approved) X01304699-P2
- Jun 4, 2026 — New job filed (Approved) X01304699-P9
- Jul 2, 2026 — Plans approved (Approved) X01304699-P9
- Aug 4, 2026 — New job filed (Approved) X01304699-A1
- Aug 4, 2026 — New job filed (Approved) X01304699-A2
- Aug 4, 2026 — New job filed (Approved) X01304699-P7
- Aug 4, 2026 — New job filed (Approved) X01304699-P8
- Aug 7, 2026 — Plans approved (Approved) X01304699-P8
- Aug 7, 2026 — Permit issued — work can start (Permit Entire) X01304699-Z2
- Aug 7, 2026 — Plans approved (Approved) X01304699-P7
- Aug 10, 2026 — Plans approved (Approved) X01304699-A2
- Aug 25, 2026 — Permit issued — work can start (Permit Entire) X01304699-I1
- Aug 25, 2026 — Plans approved (Approved) X01304699-A1
- Sep 16, 2026 — New job filed (Permit Entire) X01304699-Z8
- Sep 17, 2026 — New job filed (Approved) X01304699-A3
- Sep 17, 2026 — Permit issued — work can start (Protection and Mechanical Methods) X01304699-Z8
- Sep 18, 2026 — Permit issued — work can start (Permit Entire) X01304699-Z8
- Sep 21, 2026 — Plans approved (Approved) X01304699-A3
- Sep 21, 2026 — Permit issued — work can start (Permit Entire) X01304699-S4
- Oct 1, 2026 — Permit issued — work can start (Permit Entire) X01304699-Z1
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| X01304699-Z8-PMM | Protection and Mechanical Methods | Permit Issued | Sep 17, 2026 | Sep 17, 2027 |
| X01304699-S8-GC | General Construction | Permit Issued | Apr 12, 2026 | Dec 30, 2026 |
| X01304699-Z2-SF | Supported Scaffold | Permit Issued | Apr 12, 2026 | Apr 13, 2027 |
| X01304699-Z3-FN | Construction Fence | Permit Issued | Apr 9, 2026 | Apr 10, 2027 |
| X01304699-Z1-SH | Sidewalk Shed | Permit Issued | Apr 8, 2026 | Dec 29, 2026 |
| X01304699-S5-GC-CX | Foundation | Permit Issued | Apr 7, 2026 | Dec 30, 2026 |
| X01304699-S6-SE | Support of Excavation | Permit Issued | Apr 7, 2026 | Dec 30, 2026 |
| X01304699-S9-ST | Structural | Permit Issued | Apr 7, 2026 | Dec 30, 2026 |
| X01304699-I1-GC | General Construction | Permit Issued | Apr 6, 2026 | Dec 30, 2026 |
| X01304699-S3-PL | Plumbing | Permit Issued | Apr 6, 2026 | Apr 7, 2027 |
| X01304699-S4-ST | Structural | Permit Issued | Apr 5, 2026 | Dec 30, 2026 |
| X01304699-S1-MS | Mechanical Systems | Permit Issued | Apr 1, 2026 | Dec 30, 2026 |
Watch this block
Get an email when the next job is filed within 100 ft of this address. Free, weekly.