Neighborhoods › West New Brighton-Silver Lake-Grymes Hill › Building 5106523
Mechanical/plumbing work: Installation / retrofit of two selective catalytic…, est. $700K
355 Bard Avenue, Staten Island 10018 · Approved
| Job | S01259498 · Alteration |
|---|---|
| Category | mechanical/plumbing |
| Estimated cost | $700,000 |
| Scale | 3 → 3 stories; 1 sq ft |
| Work types | Mechanical |
| Filed | Aug 12, 2026 |
| Professional | Vanderweil Engineers |
| Building | BIN 5106523 · BBL 5001020001 |
| Official record | DOB NOW job S01259498 |
DOB description
S01259498-P1: Installation / retrofit of two selective catalytic reduction systems associated with the existing cogeneration plant
Status timeline
- Aug 12, 2026 — New job filed (Approved)
- Aug 17, 2026 — Plans approved (Approved)
Watch this block