NYC Permit AlertsBy BuildPermitGuide

Neighborhoods › Port Richmond › Building 5006175

Interior renovation: P.s. 019-r: construct a connection bridge structure…, est. $2.1M

780 Post Avenue, Staten Island 10119 · Approved

JobS01073279 (9 filings: P1, P2, P4, P6, S6, S4, P5, S5, P3) · Alteration
Categoryinterior renovation
Estimated cost$2,075,520
Scale45 → 3 stories; 2,162 sq ft
Work typesGeneral Construction
FiledNov 4, 2025
ProfessionalGannett Fleming Engineers & Archite
BuildingBIN 5006175 · BBL 5002270024
Official recordDOB NOW job S01073279

DOB description

S01073279-P1: P.S. 019-R: Construct a connection bridge structure over the existing 1-story building to extend the corridor on the second and third floors to a new building addition.
S01073279-P2: P.S. 019-R: Construct a connection bridge structure over the existing 1-story building to extend the corridor on the second and third floors to a new building addition. Cellar work as required for local sprinkle system.
S01073279-P4: P.S. 019-R: Construct a connection bridge structure over the existing 1-story building to extend the corridor on the second and third floors to a new building addition. Cellar work as required for local sprinkle system.
S01073279-P6: P.S. 019-R: Construct a connection bridge structure over the existing 1-story building to extend the corridor on the second and third floors to a new building addition. Cellar work as required for local sprinkle system.
S01073279-S6: P.S. 019-R: New 6" sprinkler water service connecting basement level to street. As required per CCD1 for Obj. #138 approved on 03/19/2025 for adjacent building connection under DOB Job Number S01075004. and new FDC pipe connections along public way.
S01073279-S4: P.S. 019-R: NEW SPRINKLER HEADS (WATER CURTAIN) AT DOORS CONNECTING TO 25 GREENLEAF AVENUE AND REPLACEMENT OF EXISTING SPRINKLER HEADS WITH NEW 1" PIPING IN BASEMENT AND FIRST FLOOR.
S01073279-P5: P.S. 019-R: Installation of Split AC & HP Units.
S01073279-S5: P.S. 019-R: REMOVE AND REPLACE EXISTING LANDSCAPING, CONCRETE PAVEMENT, ASPHALT PAVEMENT AND STEEL-FACEDCONCRETE CURB, AND EXCAVATE FOR INSTALLATION OF NEW WATER SERVICE AND REPAIR OF EXCAVATED SURFACES.
S01073279-P3: P.S. 019-R: Installation of two (2) roof drains & associated piping on new connection bridge link structure. New water service into basement level for local sprinkler system, and domestic water use.

Status timeline

Work permits

PermitWorkStatusIssuedExpires
S01073279-I1-GCGeneral ConstructionPermit IssuedAug 9, 2026Dec 30, 2026
S01073279-S2-GC-CXMechanical SystemsPermit IssuedAug 9, 2026Dec 30, 2026
S01073279-S3-PLPlumbingPermit IssuedAug 6, 2026Jan 31, 2027
S01073279-S4-EW-SPSprinklersPermit IssuedAug 6, 2026Jan 31, 2027
S01073279-S1-STStructuralPermit IssuedJul 19, 2026Dec 30, 2026