Neighborhoods › Hell's Kitchen › Building 1025410
Facade/scaffold work: Installation of temporary pipe scaffold as per plans.…, est. $28K
317 West 54 Street, Manhattan 11207 · Permit Entire
| Job | M01475114 · Alteration |
|---|---|
| Category | facade/scaffold |
| Estimated cost | $27,530 |
| Scale | 39 → 39 dwelling units; 11,012 sq ft |
| Work types | Scaffold |
| Filed | Oct 14, 2026 |
| Professional | Joel Phagoo P.E. Pllc |
| Building | BIN 1025410 · BBL 1010450020 |
| Official record | DOB NOW job M01475114 |
DOB description
M01475114-I1: INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Status timeline
- Oct 14, 2026 — New job filed (Permit Entire)
- Oct 15, 2026 — Permit issued — work can start (Supported Scaffold)
- Oct 16, 2026 — Permit issued — work can start (Permit Entire)
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01475114-I1-SF | Supported Scaffold | Permit Issued | Oct 15, 2026 | Feb 9, 2027 |
Watch this block
Get an email when the next job is filed within 100 ft of this address. Free, weekly.