Interior renovation: General construction for interior renovations, as shown…, est. $17M
250 Vesey Street, Manhattan 10001 · Permit Entire
| Job | M01370136 (7 filings: I1, P1, S1, S2, S3, S5, S4) · Alteration |
|---|---|
| Category | interior renovation |
| Estimated cost | $16,626,805 |
| Scale | 33 → 33 stories; 38,445 sq ft |
| Work types | General Construction |
| Filed | Mar 25, 2026 |
| Professional | Perkins and Will |
| Building | BIN 1000060 · BBL 1000160150 |
| Official record | DOB NOW job M01370136 |
DOB description
M01370136-I1: General construction for interior renovations, as shown on plans filed herewith. No change in use, egress, or occupancy.
M01370136-P1: General construction for interior renovations, as shown on plans filed herewith. No change in use, egress, or occupancy.
M01370136-S1: Mechanical work as shown on plans filed herewith.
M01370136-S2: Plumbing work as shown on plans filed herewith.
M01370136-S3: Sprinkler work as shown on plans filed herewith.
M01370136-S5: Structural work as shown on plans filed herewith.
M01370136-S4: Standpipe work as shown on plans filed herewith.
Status timeline
- Mar 25, 2026 — New job filed (Permit Entire) M01370136-I1
- Mar 25, 2026 — New job filed (Permit Entire) M01370136-S1
- Mar 25, 2026 — New job filed (Permit Entire) M01370136-S2
- Jul 12, 2026 — New job filed (Permit Entire) M01370136-S3
- Jul 12, 2026 — New job filed (Permit Entire) M01370136-S4
- Jul 12, 2026 — New job filed (Permit Entire) M01370136-S5
- Jul 14, 2026 — New job filed (Approved) M01370136-P1
- Jul 15, 2026 — Plans approved (Approved) M01370136-P1
- Aug 26, 2026 — Permit issued — work can start (General Construction) M01370136-I1
- Aug 26, 2026 — Permit issued — work can start (Structural) M01370136-S5
- Aug 27, 2026 — Permit issued — work can start (Permit Entire) M01370136-S5
- Aug 27, 2026 — Permit issued — work can start (Permit Entire) M01370136-I1
- Aug 27, 2026 — Permit issued — work can start (Mechanical Systems) M01370136-S1
- Aug 28, 2026 — Permit issued — work can start (Permit Entire) M01370136-S1
- Sep 15, 2026 — Permit issued — work can start (Sprinklers) M01370136-S3
- Sep 16, 2026 — Permit issued — work can start (Permit Entire) M01370136-S3
- Sep 16, 2026 — Permit issued — work can start (Standpipe) M01370136-S4
- Sep 17, 2026 — Permit issued — work can start (Permit Entire) M01370136-S4
- Sep 17, 2026 — Permit issued — work can start (Plumbing) M01370136-S2
- Sep 18, 2026 — Permit issued — work can start (Permit Entire) M01370136-S2
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01370136-S2-PL | Plumbing | Permit Issued | Sep 17, 2026 | Mar 30, 2027 |
| M01370136-S4-EW-SD | Standpipe | Permit Issued | Sep 16, 2026 | Sep 17, 2027 |
| M01370136-S3-EW-SP | Sprinklers | Permit Issued | Sep 15, 2026 | Sep 16, 2027 |
| M01370136-S1-MS | Mechanical Systems | Permit Issued | Aug 27, 2026 | Feb 14, 2027 |
| M01370136-I1-GC | General Construction | Permit Issued | Aug 26, 2026 | Feb 14, 2027 |
| M01370136-S5-ST | Structural | Permit Issued | Aug 26, 2026 | Feb 14, 2027 |