Neighborhoods › Financial District-Battery Park City › Building 1075698

Interior renovation: Alt-2 app. for installation of temporary exit door fire…, est. $75K

21 South End Avenue, Manhattan 10031 · Approved

JobM01366619 (3 filings: I1, P1, S1) · Alteration
Categoryinterior renovation
Estimated cost$75,000
Scale9 → 9 stories; 181 → 181 dwelling units; 11,000 sq ft
Work typesGeneral Construction
FiledMar 24, 2026
ProfessionalThink Wilder Llc
BuildingBIN 1075698 · BBL 1000167509
Official recordDOB NOW job M01366619

DOB description

M01366619-I1: ALT-2 app. for installation of temporary exit door Fire Exit #2 at South Cove to maintain required egress during Construction Stage 6D with flood barrier installation. Existing daycare exit will close temporarily. No change to use, egress, or occupancy.
M01366619-P1: Temporary removal/replacement of baseboard heaters and piping, relocate mechanical equipment, install DDC thermostats, and patch/repair affected finishes. All work restored after construction. No change to use, egress, or occupancy.
M01366619-S1: Temporary removal/replacement of baseboard heaters and piping, relocate mechanical equipment, install DDC thermostats, and patch/repair affected finishes. All work restored after construction. No change to use, egress, or occupancy.