Neighborhoods › Midtown South-Flatiron-Union Square › Building 1091939
Facade/scaffold work: Installation of temporary suspended scaffolds per plan submitted.…
262 5 Avenue, Manhattan 11385 · Permit Entire
| Job | M01330105 (6 filings: I1, S2, P1, P3, P4, S1) · Alteration |
|---|---|
| Category | facade/scaffold |
| Estimated cost | not stated |
| Work types | Suspended Scaffold |
| Filed | Dec 7, 2025 |
| Professional | Skyline Rigging |
| Building | BIN 1091939 · BBL 1008300044 |
| Official record | DOB NOW job M01330105 |
DOB description
M01330105-I1: INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
M01330105-S2: INSTALLATION OF TEMPORARY MATERIAL HOIST ON OUTRIGGERS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
M01330105-P1: INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
M01330105-P3: INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
M01330105-P4: INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
M01330105-S1: INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
Status timeline
- Dec 7, 2025 — New job filed (Permit Entire) M01330105-I1
- Dec 7, 2025 — Permit issued — work can start (Suspended Scaffold) M01330105-I1
- Dec 15, 2025 — New job filed (Approved) M01330105-P1
- Dec 17, 2025 — Plans approved (Approved) M01330105-P1
- Mar 1, 2026 — New job filed (Permit Entire) M01330105-S1
- Mar 3, 2026 — Permit issued — work can start (Suspended Scaffold) M01330105-S1
- Apr 3, 2026 — Permit issued — work can start (Permit Entire) M01330105-I1
- Apr 20, 2026 — New job filed (Approved) M01330105-P3
- Apr 21, 2026 — Plans approved (Approved) M01330105-P3
- Sep 25, 2026 — New job filed (Permit Entire) M01330105-S2
- Sep 27, 2026 — Permit issued — work can start (Protection and Mechanical Methods) M01330105-S2
- Sep 28, 2026 — Permit issued — work can start (Permit Entire) M01330105-S2
- Oct 6, 2026 — New job filed (Approved) M01330105-P4
- Oct 7, 2026 — Plans approved (Approved) M01330105-P4
- Oct 7, 2026 — Permit issued — work can start (Permit Entire) M01330105-S1
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01330105-S2-PMM | Protection and Mechanical Methods | Permit Issued | Sep 27, 2026 | Dec 30, 2026 |
| M01330105-S1-SC | Suspended Scaffold | Permit Issued | Mar 3, 2026 | Dec 31, 2026 |
| M01330105-I1-SC | Suspended Scaffold | Permit Issued | Dec 7, 2025 | Dec 31, 2026 |