Neighborhoods › East Harlem (South) › Building 1802897
New 3-story building
157 East 108 Street, Manhattan 10005 · Approved
| Job | M01211560 (5 filings: P1, P2, P3, S8, S9) · New Building |
|---|---|
| Category | new building |
| Estimated cost | not stated |
| Scale | — → 3 stories; 64,513 sq ft |
| Work types | Foundation, Earthwork |
| Filed | Mar 10, 2026 |
| Professional | Silman |
| Building | BIN 1802897 · BBL 1016360025 |
| Official record | DOB NOW job M01211560 |
DOB description
M01211560-P1: Related foundation work for new 3-story building for school athletic facility as per plans filed herewith.
M01211560-P2: Related SOE work for new 3-story building for school athletic facility as per plans filed herewith.
M01211560-P3: New water and sewer connections associated with M01211560-S5
M01211560-S8: INSTALLATION OF AN AIR PRESSURISED SUPERVISED TEMPORARY STANDPIPE SYSTEM AS PER PLANS SUBMITTED HEREWITH, NO CHANGE IN USE, EGRESS OR OCCUPANCY GROUP.
M01211560-S9: Suspended Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy.
Status timeline
- Mar 9, 2026 — New job filed (Approved) M01211560-P2
- Mar 10, 2026 — New job filed (Approved) M01211560-P1
- Mar 11, 2026 — New job filed (Permit Entire) M01211560-S8
- Apr 2, 2026 — Plans approved (Approved) M01211560-P2
- Apr 19, 2026 — Plans approved (Approved) M01211560-P1
- May 11, 2026 — Permit issued — work can start (Standpipe) M01211560-S8
- May 12, 2026 — Permit issued — work can start (Permit Entire) M01211560-S8
- Jun 8, 2026 — New job filed (Approved) M01211560-P3
- Jun 9, 2026 — Plans approved (Approved) M01211560-P3
- Jul 1, 2026 — Permit expired (Standpipe) M01211560-S8
- Oct 5, 2026 — New job filed (Permit Entire) M01211560-S9
- Oct 6, 2026 — Permit issued — work can start (Suspended Scaffold) M01211560-S9
- Oct 7, 2026 — Permit issued — work can start (Permit Entire) M01211560-S9
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01211560-S9-SC | Suspended Scaffold | Permit Issued | Oct 6, 2026 | Feb 20, 2027 |
| M01211560-S8-EW-SD | Standpipe | Permit Issued | May 11, 2026 | Jul 1, 2026 |
| M01211560-S6-EW-SD | Sprinklers | Permit Issued | May 3, 2026 | Jul 1, 2026 |
| M01211560-I1-GC | General Construction | Permit Issued | Apr 6, 2026 | Dec 30, 2026 |
| M01211560-S3-ST | Structural | Permit Issued | Apr 2, 2026 | Dec 30, 2026 |
| M01211560-S4-MS | Mechanical Systems | Permit Issued | Mar 31, 2026 | Jan 1, 2027 |
| M01211560-S6-EW-SP | Standpipe | Permit Issued | Mar 30, 2026 | Dec 31, 2026 |
| M01211560-S5-PL | Plumbing | Permit Issued | Feb 18, 2026 | Nov 29, 2026 |
| M01211560-S7-PL | Plumbing | Permit Issued | Dec 2, 2025 | Nov 30, 2026 |
| M01211560-S1-FO | Foundation | Permit Issued | Nov 25, 2025 | Nov 26, 2026 |
| M01211560-S2-SE | Support of Excavation | Permit Issued | Nov 25, 2025 | Dec 29, 2026 |