Neighborhoods › Upper East Side-Lenox Hill-Roosevelt Island › Building 1091943
New 31-story building, 88 units, est. $1K
1484 1 Avenue, Manhattan 10016 · Approved
| Job | M01128646 (9 filings: Z2, P4, P5, P6, P7, P8, P9, Z3, Z4) · New Building |
|---|---|
| Category | new building |
| Estimated cost | $1,000 |
| Scale | — → 31 stories; — → 88 dwelling units; 168,875 sq ft |
| Work types | — |
| Filed | Dec 30, 2025 |
| Professional | Meyers+ Engineers |
| Building | BIN 1091943 · BBL 1014720003 |
| Official record | DOB NOW job M01128646 |
DOB description
M01128646-Z2: INSTALLATION OF 3 NEW GAS FIRE BOILERS IN CONJUNCTION WITH NEW BUILDING M01128646-I1
M01128646-P4: Foundation work in conjunction with NB # M01128646
M01128646-P5: Support of excavation in conjunction with NB # M01128646-I1
M01128646-P6: Underpinning in conjunction with NB # M01128646-I1
M01128646-P7: Underpinning in conjunction with NB # M01128646-I1
M01128646-P8: Structural work in conjunction with NB # M01128646
M01128646-P9: Plumbing work in conjunction with NB # M01128646
M01128646-Z3: INSTALLATION AND USE OF TEMPORARY EXTERIOR CLIMBING PLATFORMS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M01128646-Z4: PMM filed for temporary field offices.
Status timeline
- Nov 23, 2025 — New job filed (Approved) M01128646-P4
- Nov 23, 2025 — New job filed (Approved) M01128646-P5
- Nov 23, 2025 — New job filed (Approved) M01128646-P6
- Nov 28, 2025 — Plans approved (Approved) M01128646-P6
- Dec 5, 2025 — Plans approved (Approved) M01128646-P5
- Dec 20, 2025 — Plans approved (Approved) M01128646-P4
- Dec 30, 2025 — New job filed (Approved) M01128646-Z2
- Jan 10, 2026 — New job filed (Approved) M01128646-P7
- Jan 13, 2026 — Plans approved (Approved) M01128646-P7
- Feb 9, 2026 — New job filed (Approved) M01128646-P8
- Mar 11, 2026 — Plans approved (Approved) M01128646-P8
- Mar 28, 2026 — Plans approved (Approved) M01128646-Z2
- May 25, 2026 — New job filed (Permit Entire) M01128646-Z3
- Jul 19, 2026 — New job filed (Permit Entire) M01128646-Z4
- Jul 27, 2026 — Permit issued — work can start (Protection and Mechanical Methods) M01128646-Z4
- Jul 28, 2026 — Permit issued — work can start (Permit Entire) M01128646-Z4
- Aug 3, 2026 — Permit issued — work can start (Protection and Mechanical Methods) M01128646-Z3
- Aug 4, 2026 — Permit issued — work can start (Permit Entire) M01128646-Z3
- Aug 18, 2026 — New job filed (Approved) M01128646-P9
- Sep 21, 2026 — Plans approved (Approved) M01128646-P9
Work permits
| Permit | Work | Status | Issued | Expires |
|---|---|---|---|---|
| M01128646-S6-MS | Mechanical Systems | Permit Issued | Oct 4, 2026 | Nov 8, 2026 |
| M01128646-Z3-PMM | Protection and Mechanical Methods | Permit Issued | Aug 3, 2026 | Dec 19, 2026 |
| M01128646-Z4-PMM | Protection and Mechanical Methods | Permit Issued | Jul 27, 2026 | Nov 30, 2026 |
| M01128646-S5-FN | Construction Fence | Permit Issued | Jul 19, 2026 | Nov 30, 2026 |
| M01128646-S8-EW-SD | Standpipe | Permit Issued | Jun 11, 2026 | Nov 18, 2026 |
| M01128646-S8-EW-SP | Sprinklers | Permit Issued | Jun 11, 2026 | Nov 18, 2026 |
| M01128646-I1-GC | General Construction | Permit Issued | Mar 11, 2026 | Nov 30, 2026 |
| M01128646-S7-PL | Plumbing | Permit Issued | Jan 19, 2026 | Jan 20, 2027 |
| M01128646-Z1-PL | Plumbing | Permit Issued | Nov 23, 2025 | Nov 24, 2026 |
| M01128646-S1-FO | Foundation | Permit Issued | Nov 17, 2025 | Dec 1, 2026 |
| M01128646-S9-EW-SD | Standpipe | Permit Issued | Nov 13, 2025 | Nov 18, 2026 |
| M01128646-S2-ST | Structural | Permit Issued | Oct 29, 2025 | Nov 30, 2026 |
| M01128646-S4-FO | Foundation | Permit Issued | Oct 29, 2025 | Nov 30, 2026 |
| M01128646-S3-SE | Support of Excavation | Permit Issued | Oct 28, 2025 | Nov 30, 2026 |