Neighborhoods › East Williamsburg › Building 3071199
Interior renovation: Selective removals of existing: bulkhead…, est. $8.5M
108 Montrose Avenue, Brooklyn 10018 · Approved
| Job | B01339631 (11 filings: I1, P3, S1, P1, P2, S3, P4, S2, S6, P5, S5) · Alteration |
|---|---|
| Category | interior renovation |
| Estimated cost | $8,500,000 |
| Scale | 3 → 3 stories; 9,000 sq ft |
| Work types | General Construction |
| Filed | Dec 25, 2025 |
| Professional | Velocity Architectural Services Pll |
| Building | BIN 3071199 · BBL 3030600001 |
| Official record | DOB NOW job B01339631 |
DOB description
B01339631-I1: Selective Removals of Existing: Bulkhead (Doors/Frames), Metal Coping, Window A/C Units; Replacement of Existing Roof Coverings, Railings, Roof Drains, Louvers, Coping Stones/Flashing, New: Roof System, Railings, Bulkhead, Roof Drains, Insulated Windows
B01339631-P3: SELECTIVE REMOVALS OF EXISTING VENTILATORS, STEAM RADIATORS, AHU, 127 STEAM FINTUBE RADIATORS, EXHAUST FANS, ROOF MOUNTED CHILLER;, MECHANICAL UNIT INSTALLATION AS PER DESIGN PLANS SUMMARY OF WORK.
B01339631-S1: SELECTIVE REMOVALS OF EXISTING VENTILATORS, STEAM RADIATORS, AHU, 127 STEAM FINTUBE RADIATORS, EXHAUST FANS, ROOF MOUNTED CHILLER;, MECHANICAL UNIT INSTALLATION AS PER DESIGN PLANS SUMMARY OF WORK.
B01339631-P1: Selective Removals of Existing: Bulkhead (Doors/Frames), Metal Coping, Window A/C Units; Replacement of Existing Roof Coverings, Railings, Roof Drains, Louvers, Coping Stones/Flashing, New: Roof System, Railings, Bulkhead, Roof Drains, Insulated Windows
B01339631-P2: NEW STEEL DUNNAGE PLATFORM WITH SCREEN-WALL, SERVICE PLATFORM and STAIR ON ROOF. NEW STEEL FRAMING TO REINFORCE SLAB AROUND NEW SLAB OPENINGS, INFILL EXISTING SLAB OPENINGS.
B01339631-S3: NEW STEEL DUNNAGE PLATFORM WITH SCREEN-WALL, SERVICE PLATFORM and STAIR ON ROOF. NEW STEEL FRAMING TO REINFORCE SLAB AROUND NEW SLAB OPENINGS, INFILL EXISTING SLAB OPENINGS.
B01339631-P4: SELECTIVE REMOVALS OF GAS METER PIPING, HOT WATER HEATER, BOILER PILOTS, EXISTING CLASSROOM SINKS, ROOF DRAINS, ROOF VENTS AND INSTALL NEW HEAT PUMPS, TEMP ELECTRIC WATER HEATER, ROOF DRAINS, SUMP PUMP, VTRS, CLASSROOM SINKS.
B01339631-S2: SELECTIVE REMOVALS OF GAS METER PIPING, HOT WATER HEATER, BOILER PILOTS, EXISTING CLASSROOM SINKS, ROOF DRAINS, ROOF VENTS AND INSTALL NEW HEAT PUMPS, TEMP ELECTRIC WATER HEATER, ROOF DRAINS, SUMP PUMP, VTRS, CLASSROOM SINKS.
B01339631-S6: REMOVAL OF EXISTING TWO (2) 7500 GALLONS FUE OIL TANKS. REFER TO MECHANICAL FILING FOR REMOVAL OF FUEL OIL PUMPS, POWER CONNECTIONS, CONTROLS AND ANCILLARY EQUIPMENT.
B01339631-P5: Shutdown Entire Sprinkler System provide Fire Watch, Selective Removals of Existing Sprinkler Branch, Riser and 6 Sprinkler Heads, Install New Tamper Switches, Flow Switch, 2" Sprinkler Drain/Tie-In, New Inspector Test Connection.
B01339631-S5: Shutdown Entire Sprinkler System provide Fire Watch, Selective Removals of Existing Sprinkler Branch, Riser and 6 Sprinkler Heads, Install New Tamper Switches, Flow Switch, 2" Sprinkler Drain/Tie-In, New Inspector Test Connection.
Status timeline
- Dec 25, 2025 — New job filed (Approved) B01339631-I1
- Dec 25, 2025 — New job filed (Approved) B01339631-S1
- Dec 25, 2025 — New job filed (Approved) B01339631-S2
- Dec 25, 2025 — New job filed (Approved) B01339631-S3
- Dec 25, 2025 — New job filed (Approved) B01339631-S5
- Jan 28, 2026 — New job filed (Approved) B01339631-S6
- Apr 17, 2026 — Plans approved (Approved) B01339631-S6
- May 7, 2026 — New job filed (Approved) B01339631-P1
- May 7, 2026 — New job filed (Approved) B01339631-P2
- May 11, 2026 — Plans approved (Approved) B01339631-P1
- May 11, 2026 — Plans approved (Approved) B01339631-I1
- May 12, 2026 — Plans approved (Approved) B01339631-P2
- May 12, 2026 — Plans approved (Approved) B01339631-S3
- Sep 10, 2026 — New job filed (Approved) B01339631-P3
- Sep 21, 2026 — Plans approved (Approved) B01339631-P3
- Sep 21, 2026 — Plans approved (Approved) B01339631-S1
- Oct 4, 2026 — New job filed (Approved) B01339631-P4
- Oct 4, 2026 — New job filed (Approved) B01339631-P5
- Oct 8, 2026 — Plans approved (Approved) B01339631-P4
- Oct 8, 2026 — Plans approved (Approved) B01339631-S2
- Oct 8, 2026 — Plans approved (Approved) B01339631-P5
- Oct 8, 2026 — Plans approved (Approved) B01339631-S5